Schedule
For New
Residential Construction
| A Sample Residential
Construction Schedule -
(for a 6,000 square foot custom
home)
How long does it take to
build a house? Scroll down this page to see an example of a
typical construction schedule for a large custom home. It
was produced using Microsoft Project® 4.1
scheduling software and includes most, but not all, of the
activities involved in the process of building a new house.
Sample construction draws have been included for reference
purposes, although individual lenders & mortgage
companies will most likely have their own draw
schedules.
Notice that because
construction draws from the lender typically follow the
completion of various phases, or milestones, the cash flow
on a project can be very irregular. While the money flowing
out of a construction company; for employee salaries,
benefits, office space, vehicles, insurance, equipment and
other company expenses, typically occurs on a regular
calendar based timeline, the money used to pay these
expenses follows an event driven schedule. Therefore,
besides the "normal" unplanned events that can affect the
progress of a home building project, it is not uncommon for
home builders to rearrange construction schedules in order
to gain access to draw money so that they are able to pay
subcontractors and suppliers in a timely manner. By the way,
this is generally a good thing (provided you have an honest
builder) because subcontractors tend to follow the money and
happy subs are almost always preferable to unhappy ones:-)
Will your house take
this long to build?
Probably not; most home
building projects will take less time, but some will take
even more. For example, the timeline for a smaller house,
with few options and less detailed finishes, which has been
built many times before by professional builders, might be
as short as 8 to 12 weeks. However, 6 to 9 months from start
to finish is probably a more realistic average. While a
larger house, with more options, custom features, fancier
finishes, and more owner involvement -- especially if the
owner has little construction experience -- may very well
take 1 1/2 to 2 years to complete. Then again, if you build
your own house, and make the common mistake of moving in
before every last detail is finished, well, you might be
looking at decades instead of months or years --- Some quick
and dirty production builders throw up a house in only three
or four months.
The schedule can be impacted
by availability of capital, labor and materials. The biggest
problem is the cost cutting measures by builders who want to
maximize profits by minimizing quality. The areas that are
often cut relate to using an incompetent or insufficiently
trained labor force. Much of the actual labor consists of
day labor aliens (most from Mexico) who can not
read, write or speak sufficient English. It is a formula
that invites much disaster. Construction sites are often
crime zones.
The actual schedule of
completion for a specific project will vary based upon many
factors including, but not limited to, size and degree of
difficulty of the structure, site and weather conditions,
material and contractor availability, crew sizes, effective
scheduling and communication, the knowledge and experience
of those managing the project, and perhaps most
significantly, the number, timeliness, and complexity of the
changes you will inevitably make to the original contract
after construction has already begun.
|
| ID |
Outline Number |
Name |
Duration |
Predecessors |
| 1 |
1 |
Contracts |
0.00d |
. |
| 2 |
1.1 |
__Supply
Lot Sale Agreement |
0.00d |
. |
| 3 |
1.2 |
__Supply
Construction Agreement |
0.00d |
. |
| 4 |
1.3 |
__Supply
Contract Plans |
0.00d |
3 |
| 5 |
1.4 |
__Supply
Contract Specifications |
0.00d |
3 |
| 6 |
1.5 |
__Supply
Contract Site Plan |
0.00d |
3 |
| 7 |
1.6 |
__Secure
Financing |
0.00d |
. |
| 8 |
1.7 |
__Construction
Loan Settlement |
0.00d |
. |
| 9 |
2 |
Document Review
& Revision |
25.00d |
. |
| 10 |
2.1 |
__Review
& Finalize Plans |
15.00d |
4 |
| 11 |
2.2 |
__Review
& Finalize Specifications |
20.00d |
5 |
| 12 |
2.3 |
__Review
& Finalize Site Plan |
1.00d |
6,10 |
| 13 |
2.4 |
__Print
Construction Drawings |
5.00d |
10,11,12 |
| 14 |
2.5 |
__Approve
Revised Plans |
0.00d |
13 |
| 15 |
2.6 |
__Approve
Revised Specifications |
0.00d |
13 |
| 16 |
2.7 |
__Approve
Revised Site Plan |
0.00d |
13 |
| 17 |
3 |
Bids &
Contracts |
24.00d |
. |
| 18 |
3.1 |
__Make
Copies of Plans |
3.00d |
14 |
| 19 |
3.2 |
__Make
Copies of Specifications |
2.00d |
15 |
| 20 |
3.3 |
__Distribute
Plans & Specifications |
1.00d |
18,19 |
| 21 |
3.4 |
__Receive
Bids |
10.00d |
20 |
| 22 |
3.5 |
__Review Bids |
5.00d |
. |
| 25 |
3.6 |
__Execute
Subcontractor Agreements |
5.00d |
23 |
| 26 |
4 |
Grading &
Building Permits |
17.00d |
. |
| 27 |
4.1 |
__Schedule
lot stake-out |
1.00d |
13 |
| 28 |
4.2 |
__Stake
lot |
1.00d |
27FS+3d |
| 29 |
4.3 |
__File
Grading Permit Application |
1.00d |
16 |
| 30 |
4.4 |
__File
Building Permit Application |
3.00d |
14,15,16 |
| 31 |
4.5 |
__Post
Lot Identification |
1.00d |
28,29,30 |
| 32 |
4.6 |
__Meet
Sed. Control Insp. |
1.00d |
29FS+2d,28,31 |
| 33 |
4.7 |
__Walk
Lot w/ Owner |
1.00d |
32 |
| 34 |
4.8 |
__Install
Construction Entrance |
1.00d |
32,33 |
| 35 |
4.9 |
__Install
Sediment Controls |
2.00d |
32,33 |
| 36 |
4.10 |
__Sediment
Control Insp. |
1.00d |
34,35 |
| 37 |
4.11 |
__Grading
Permit Issued |
1.00d |
36 |
| 38 |
4.12 |
__County
Permit Process |
10.00d |
30 |
| 39 |
4.13 |
__Building
Permit Approved |
1.00d |
38,37 |
| 40 |
4.14 |
__Pay
Permit Fees and Excise Taxes |
1.00d |
39FS+2d |
| 41 |
4.15 |
__Building
Permit Issued |
0.00d |
40 |
| 42 |
5 |
Site Work |
7.00d |
. |
| 43 |
5.1 |
__Clear
Lot |
3.00d |
37 |
| 44 |
5.2 |
__Strip
Topsoil & Stockpile |
1.00d |
43 |
| 45 |
5.3 |
__Stake
Lot for Excavation |
1.00d |
43 |
| 46 |
5.4 |
__Rough
grade lot |
1.00d |
43,45 |
| 47 |
5.5 |
__Excavate
for foundation |
2.00d |
39,45,43,46 |
| 48 |
6 |
Foundation |
24.00d |
. |
| 49 |
6.1 |
__Layout
footings |
1.00d |
47 |
| 50 |
6.2 |
__Dig
Footings & Install Reinforcing |
1.00d |
49 |
| 51 |
6.3 |
__Footing
Inspection |
0.00d |
50 |
| 52 |
6.4 |
__Pour
footings |
1.00d |
51 |
| 53 |
6.5 |
__Pin
Footings |
1.00d |
52 |
| 54 |
6.6 |
__Stock
Block, Mortar, Sand |
1.00d |
53 |
| 55 |
6.7 |
__Build
Block Foundation |
15.00d |
53,54 |
| 56 |
6.8 |
__Foundation
Certification |
0.00d |
55 |
| 57 |
6.9 |
__Draw #1 (Location Survey) |
0.00d |
56 |
| 58 |
6.10 |
__Fill
Block Cores w/ Concrete |
1.00d |
55 |
| 59 |
6.11 |
__Steel
Delivery |
1.00d |
58 |
| 60 |
6.12 |
__Set
Lintels, Bolts, Cap Block |
2.00d |
59 |
| 61 |
6.13 |
__Lumber
Delivery |
1.00d |
58 |
| 62 |
6.14 |
__Waterproofing
and Drain Tile |
1.00d |
61 |
| 63 |
7 |
Rough Carpentry |
44.00d |
. |
| 64 |
7.1 |
__Set
Steel |
1.00d |
60 |
| 65 |
7.2 |
__1st
Floor Deck Framing |
4.00d |
64 |
| 66 |
7.3 |
__1st
Floor Wall Framing |
4.00d |
65 |
| 67 |
7.4 |
__Draw #2 (First Floor Deck) |
0.00d |
66 |
| 68 |
7.5 |
__2nd
Floor Deck Framing |
2.00d |
67 |
| 69 |
7.6 |
__Draw #3 (Second Floor
Deck) |
0.00d |
68 |
| 70 |
7.7 |
__2nd
Floor Wall Framing |
3.00d |
69 |
| 71 |
7.8 |
__Set
Roof Trusses |
2.00d |
70 |
| 72 |
7.9 |
__Frame
Roof |
7.00d |
71 |
| 73 |
7.10 |
__Install
Roof Plywood |
5.00d |
72 |
| 74 |
7.11 |
__Install
Windows & Doors |
2.00d |
73,111 |
| 75 |
7.12 |
__Frame
Basement |
3.00d |
72,81 |
| 76 |
7.13 |
__Frame
Basement Bulkheads |
2.00d |
75,87,93 |
| 77 |
8 |
Concrete Slabs |
8.00d |
. |
| 78 |
8.1 |
__Basement
Slab Preparation |
2.00d |
65,91 |
| 79 |
8.2 |
__Termite
Treatment Basement Slab |
1.00d |
78 |
| 80 |
8.3 |
__Slab
Inspection |
1.00d |
79 |
| 81 |
8.4 |
__Pour
Basement Slab |
1.00d |
80 |
| 82 |
8.5 |
__Prep
Garage Slab |
1.00d |
81 |
| 83 |
8.6 |
__Termite
Treatment Garage Slab |
1.00d |
82 |
| 84 |
8.7 |
__Pour
Garage Slab |
1.00d |
83 |
| 85 |
9 |
H.V.A.C. |
17.00d |
. |
| 86 |
9.1 |
__HVAC
Layout & Measure |
1.00d |
72 |
| 87 |
9.2 |
__HVAC
Rough-in |
5.00d |
86,111 |
| 88 |
9.3 |
__HVAC
Set Indoor Units |
2.00d |
81,87 |
| 89 |
9.4 |
__HVAC
Temporary Heat |
2.00d |
88 |
| 90 |
10 |
Plumbing
Rough-in |
37.00d |
. |
| 91 |
10.1 |
__Plumbing
Sub-slab |
2.00d |
65 |
| 92 |
10.2 |
__Plumbing
Layout |
1.00d |
91,87 |
| 93 |
10.3 |
__Plumbing
rough-in |
5.00d |
92 |
| 94 |
11 |
County Plumbing Sub-slab
Inspection |
0.00d |
91 |
| 95 |
12 |
County Plumbing Rough-in
Inspection |
0.00d |
93 |
| 96 |
13 |
Electric
Rough-in |
19.00d |
. |
| 97 |
13.1 |
__Set
Electric Boxes |
2.00d |
74 |
| 98 |
13.2 |
__Install
Electric Service Panel |
2.00d |
97 |
| 99 |
13.3 |
__Electrical
Walk-through |
1.00d |
98 |
| 100 |
13.4 |
__Electrical
Rough-wire |
14.00d |
99 |
| 101
|
14 |
Specialty
Rough-ins |
5.00d |
. |
| 102 |
14.1 |
__Central
Vacuum Rough-in |
5.00d |
100 |
| 103 |
14.2 |
__Alarm
System Rough-in |
5.00d |
100 |
| 104 |
14.3 |
__Telephone
System Rough-in |
5.00d |
100 |
| 105 |
14.4 |
__Television
System Rough-in |
5.00d |
100 |
| 106 |
14.5 |
__Audio
Visual Rough-in |
5.00d |
100 |
| 107 |
15 |
County Electrical inspection |
0.00d |
96,101 |
| 108
|
16 |
Draw #5
(Rough-ins complete) |
0.00d |
95,107 |
| 109 |
17 |
County Framing Inspection |
0.00d |
95FS+1d,107FS+1d |
| 110
|
18 |
Roofing |
68.00d |
. |
| 111 |
18.1 |
__Roofing
Paper Installed |
3.00d |
73 |
| 112
|
18.2 |
__Draw #4 (Roof, windows,
doors) |
0.00d |
74,111 |
| 113 |
18.3 |
__Stock
Roof Shingles |
1.00d |
112 |
| 114 |
18.4 |
__Install
Roof Shingles |
7.00d |
113,119 |
| 115
|
19 |
Exterior
Finishes |
56.00d |
. |
| 116 |
19.1 |
__Siding |
3.00d |
74 |
| 117 |
19.2 |
__Exterior
Trim |
7.00d |
116 |
| 118 |
19.3 |
__Brick
Arch Forms |
1.00d |
117 |
| 119 |
19.4 |
__Brick
Veneer |
45.00d |
118 |
| 120
|
20 |
Insulation |
5.00d |
. |
| 121 |
20.1 |
__Caulk
& Air Seal |
1.00d |
109 |
| 122 |
20.2 |
__Draft
& Fire Stop |
1.00d |
121 |
| 123 |
20.3 |
__Batt
Insulation |
3.00d |
121,122 |
| 124 |
21 |
County Insulation Inspection |
0.00d |
123,120 |
| 125 |
22 |
BGE Energy Wise Inspection |
0.00d |
124 |
| 126
|
23 |
Drywall |
26.00d |
. |
| 127 |
23.1 |
__Stock
Drywall |
1.00d |
124 |
| 128 |
23.2 |
__Hang
Drywall |
5.00d |
127 |
| 129 |
23.3 |
__Remove
Scrap Drywall |
1.00d |
128 |
| 130 |
23.4 |
__Tape
and Finish Drywall |
15.00d |
128,129 |
| 131 |
23.5 |
__Sand
Drywall |
1.00d |
130 |
| 132 |
23.6 |
__Drywall
Point-up |
3.00d |
131 |
| 133
|
24 |
Draw #6
(Insulation & drywall applied) |
0.00d |
128,126 |
| 134
|
25 |
Floor Finishes |
76.00d |
. |
| 135 |
25.1 |
__Ceramic
Tile |
15.00d |
142 |
| 136 |
25.2 |
__Install
Hardwood Floor |
4.00d |
146 |
| 137 |
25.3 |
__Sand,
Stain, Seal Hardwood |
5.00d |
196 |
| 138 |
25.4 |
__Install
Carpet |
4.00d |
137 |
| 139 |
25.5 |
__Final
Coat Hardwood |
2.00d |
196 |
| 140
|
26 |
Paint |
59.00d |
. |
| 141 |
26.1 |
__Prep
Drywall for Prime Coat |
2.00d |
131 |
| 142 |
26.2 |
__Prime
Paint Drywall |
2.00d |
141 |
| 143 |
26.3 |
__Prep
Trim for Prime Coat |
2.00d |
142,152 |
| 144 |
26.4 |
__Prime
Trim |
2.00d |
143 |
| 145 |
26.5 |
__Finish
Coat Trim |
10.00d |
144,156 |
| 146 |
26.6 |
__Finish
Coat Drywall |
14.00d |
145,132 |
| 147 |
26.7 |
__Caulk
Exterior Windows & Doors |
1.00d |
146,117 |
| 148 |
26.8 |
__Finish
Coat Exterior Trim & Siding |
1.00d |
147 |
| 149
|
27 |
Draw #7
(Roofing, masonry, siding) |
0.00d |
114,157 |
| 150
|
28 |
Interior Trim |
29.00d |
. |
| 151 |
28.1 |
__Interior
Trim Delivery |
1.00d |
142 |
| 152 |
28.2 |
__Install
Interior Doors |
5.00d |
151 |
| 153 |
28.3 |
__Install
Interior Trim |
15.00d |
152 |
| 154 |
28.4 |
__Install
Cabinetry |
5.00d |
153 |
| 155 |
28.5 |
__Install
Appliances |
1.00d |
154 |
| 156 |
28.6 |
__1st
Punch-out Interior Trim |
2.00d |
155,144 |
| 157
|
29 |
H.V.A.C. Trim |
1.00d |
140 |
| 158 |
29.1 |
__Install
Grills & Registers for Paint |
1.00d |
131 |
| 159 |
29.2 |
__Set
Outdoor Units |
1.00d |
165 |
| 160
|
30 |
Plumbing Trim |
5.00d |
. |
| 161 |
30.1 |
__Set
Fixtures |
4.00d |
135,136,146,154 |
| 162 |
30.2 |
__Connect
Appliances |
1.00d |
161 |
| 163 |
31 |
County Final Plumbing Inspection |
0.00d |
160 |
| 164
|
32 |
Exterior
Landscaping |
32.00d |
. |
| 165 |
32.1 |
__Rough
Final Grade |
1.00d |
119 |
| 166 |
32.2 |
__Patios |
7.00d |
165,119 |
| 167 |
32.3 |
__Porches |
5.00d |
166,119 |
| 168 |
32.4 |
__Sidewalks |
7.00d |
167,119 |
| 169 |
32.5 |
__Decks |
7.00d |
168,119 |
| 170 |
32.6 |
__Driveways |
2.00d |
165,169 |
| 171 |
32.7 |
__Final
Grade and Seed |
3.00d |
170,166,167,168 |
| 172
|
33 |
Electrical
Final Trim |
160.00d |
. |
| 173 |
33.1 |
__Switch
& Plug |
2.00d |
142,100 |
| 174 |
33.2 |
__Install
Fixtures |
1.00d |
. |
| 175 |
33.3 |
__Connect
Appliances |
1.00d |
. |
| 176
|
34 |
Hardware |
12.00d |
. |
| 177 |
34.1 |
__Door
Hardware |
2.00d |
145,146 |
| 178 |
34.2 |
__Bath
Hardware |
2.00d |
145,146 |
| 179 |
34.3 |
__Mirrors |
5.00d |
178 |
| 180 |
34.4 |
__Shower
Doors |
10.00d |
178 |
| 181
|
35 |
Draw #8 (Prime
paint, cabinets, doors) |
0.00d |
142,152,154 |
| 182
|
36 |
Draw #9 (Trim,
furnace, hrdwd, tile, rails) |
0.00d |
153,181 |
| 183
|
37 |
Draw #10
(Plumbing & elec. trim, final paint) |
0.00d |
146,182 |
| 184 |
38 |
Final Building Inspection |
0.00d |
183 |
| 185 |
39 |
Use & Occupancy Certificate |
0.00d |
184FS+3d |
| 186 |
40 |
First Walk-thru |
0.00d |
185 |
| 187
|
41 |
Draw #11 (Final
payment per contract) |
0.00d |
186 |
| 188
|
42 |
Final Punch-out |
9.00d |
. |
| 189 |
42.1 |
__Punch
Out Walk-thru List |
4.00d |
186 |
| 190 |
42.2 |
__Trim
and Adjust Doors |
2.00d |
184,189 |
| 191 |
42.3 |
__Paint
Touch-up |
3.00d |
190 |
| 192
|
43 |
Cleaning |
14.00d |
. |
| 193 |
43.1 |
__Windows |
3.00d |
145,146 |
| 194 |
43.2 |
__Rough
Clean |
3.00d |
193 |
| 195 |
43.3 |
__Final
Clean |
2.00d |
176,188 |
| 196
|
44 |
Final
Walk-through |
0.00d |
187,188,192 |
| 197
|
45 |
Move-in |
0.00d |
196FS+1d |
|
|
|